PM 4.02 Estimating Vocabulary

AB
Estimate ResourcesThis is a process of estimating the type and quantities of material, etc
Schedule Management PlanIdentifies the level of accuracy and the units of measure for the resources to be estimated
Activity ListIdentifies the activities which will need resources
Activity AttributesPrimary data input for use in estimating those resources required for each activity in the activity list
Bottom-Up EstimatingWhen an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail.
Project Management SoftwareHas the capability to help plan, organize, and manage resource pools and develop resource elements
Analogous EstimatingUses parameters such as duration, budget, size, weight and complexity, from a previous, similar project,
Parametric EstimatingUses a statistical relationship between historical data and other variables to calculate an estimate for activity parameters, such as cost, budget, and duration.
PERTProgram Evaluation and Review Technique
Three-point estimatesThe accuracy of activity duration estimates can be improved by considering estimation uncertainty and risk.
Most Likely(tM)realistic expectations
Optimistic (tO)best-case scenario
Pessimistic (tp)worst-case scenario
Expected TimetE=(tO+4tM+tP)/6
Reserve AnalysisDuration estimates may include contingency reserves (knowns and unknowns)